PPAP scope planner: what do I submit at which level?

Pick the level, answer three questions about the part, and see all 18 elements marked submit, on file or not applicable. No sign-up and no upload: it runs in your browser.

Which level does your customer ask for?

If the order says nothing, level 3 is what is meant.

What applies to your part?

Your scope Level 3

For this part 14 documents are submitted and 0 kept on file.

No.ElementStatus
1 Design Records

the customer's drawing at the correct revision, ballooned: every dimension numbered

Submit
2 Authorized Engineering Change Documents

the engineering change notices that apply to this revision

Submit
3 Engineering Approval

sign-off by the customer's engineering, sometimes after trials with production parts

Submit
4 Design FMEA

failure modes of the design – only where the supplier owns the design

Submit
5 Process Flow Diagram

every manufacturing step in sequence, from raw material to packaging

Submit
6 Process FMEA

what can go wrong at each step and what is done about it

Submit
7 Control Plan

per characteristic: what is measured, with what, how often, by whom, and the reaction

Submit
8 Measurement System Analysis

evidence that gauge variation is small against the tolerance (gauge R&R)

Submit
9 Dimensional Results

every characteristic with nominal, tolerance, readings and verdict – the report itself

Submit
10 Material and Performance Test Results

material certificate with composition and strength, plus tests such as hardness, torque, leak and corrosion

Submit
11 Initial Process Studies

statistical study of the special characteristics: Pp/Ppk first, Cp/Cpk later

Submit
12 Qualified Laboratory Documentation

proof the laboratory is accredited (ISO/IEC 17025) or approved by the customer

Submit
13 Appearance Approval Report

only where colour, gloss or surface appearance is specified – rarely on turned parts

Submit
14 Sample Production Parts

the physical parts, labelled and traceable to the report

Submit
15 Master Sample

one part signed by both sides and kept for comparison

Submit
16 Checking Aids

purpose-built gauges and fixtures, with photographs and calibration records

Submit
17 Customer-Specific Requirements

whatever the customer adds: portals, formats, material data, company standards

Submit
18 Part Submission Warrant (PSW)

the cover sheet: what is submitted, why, at which level, signed

Submit

Commonly required as well in Europe

Not part of the 18, but regularly asked for:

  • IMDS – the material data sheet in the International Material Data System; without an accepted entry European carmakers generally do not approve
  • EN 10204 material certificate – which type – 3.1 is common – is stated in the order; the heat number must match the sample parts
  • Packaging approval – container, quantity and label, signed off by the customer
  • Technical cleanliness – to VDA 19 or ISO 16232, typical for hydraulic and injection parts
  • Calibration records – for every gauge that appears in the report
  • Substance declarations – RoHS, REACH and conflict minerals
  • Requalification – re-checking every characteristic during series production, often yearly

The mapping from level to scope reflects common practice. What governs is your customer's requirement matrix: at any level it can ask for more or less, and it wins. We reproduce no AIAG form – this list is our own presentation.

How to read the three states

Submit
goes to the customer with the package – as a file in their portal or in the PDF set.
On file
must be complete and current at your site. The customer may ask for it at any time or want to see it in an audit; “we don't have one” is a finding.
Not applicable
does not apply to this part. Write it on the warrant anyway, with the reason. A blank field draws more questions than “n/a, built to customer drawing”.

The three most common rejections

  1. Wrong drawing revision. The report cites an index the customer has since changed. Check the revision on the day you submit, not the day you measured.
  2. Balloon numbers do not match the report. Once the stamped drawing and the table drift apart, nobody reads any further.
  3. Too few parts. The dimensional report normally needs at least six; a capability statement needs far more.